Illumina’s R&D building construction faced several mechanical issues that delayed interior finish installation by four weeks. Further delay ensued when the original Graph Grid Panel System vendor rejected use of the TorZo panel due to panel instability. The architect and
millwork contractor turned to Averve’s Railset Web Panel System with the following results.